The following information describes how changing work hours on a Task or changing the Task 
               		Status impact the Story/Task. 
               	 
            
 
            	 
             
               		
               - When the first work record is entered, the Task 
                  		  Status is changed to 
                  		  In Progress. 
                  		
               
- The amount of time entered in the 
                  		  Worked field is automatically deducted from the 
                  		  To Do field. 
                  		
               
- When a Task is marked 
                  		  Complete, 
                  		  To Do goes to 0. Likewise, when you enter 
                  		  0 in 
                  		  To Do, the Task 
                  		  Status is set to 
                  		  Complete. 
                  		
               
- When 
                  		  Worked entered is greater than remaining 
                  		  To Do, 
                  		  To Do goes to 0. 
                  		
               
- When a Task is estimated or work records are added, these values are saved and are available to see when you select the 
                  		  Owner field of the Task. For more information, see 
                  		  Assigning and Estimating Tasks.