The next step is to add manual testers to our testing cycle. We are also going to define the capacity each manual tester has
               for this testing cycle. 
               	 
            
 
            	 
            
               -  
                  		  In the header of our testing cycle 
                     			 Week 21 - Team A, click 
                     			 . 
                     		   
                  		   The 
                  			 Edit Assigned Testers dialog box appears. 
                  		   
                  		
               
-  
                  		  Click 
                     			 Add/Remove Testers. 
                     		   
                  		   The 
                  			 Add/Remove Testers dialog box appears. 
                  		   
                  		
               
-  
                  		  Select a user group from the 
                     			 Available list. 
                     		   
                  		
               
-  
                  		  Select one or more users from the user group in the 
                     			 Available list. 
                     		   
                  		
               
-  
                  		  Click 
                     			 Add or 
                     			 Add All to add users to the 
                     			 Selected list. 
                     		   
                  		
               
-  
                  		  Click 
                     			 OK. 
                     		   
                  		   The users are now added to the list in the 
                  			 Edit Assigned Testers dialog box. 
                  		   
                  		
               
-  
                  		  For each user that was added, provide a capacity for the testing cycle in the 
                     			 Capacity field using the 
                     			 hh:mm format. 
                     		   
                  		
               
-  
                  		  Click 
                     			 Close. 
                     		   
                  		
               
Now our testing cycle shows the available resources, both for the whole testing cycle as well as for each manual tester. A
               burn-down chart displays the assigned tests that are not yet completed. After we have created our testing cycle and added
               manual testers, we can determine which tests need to be done in the next step.